Friday, August 4, 2017

HVAC, Mechanical, Electrical, and Masonry Work

HVAC equipment replacement is nearly complete in Wilmot Hall. The final control works are being wrapped up.

The mechanical contractors are installing duct work in the Performance Hall. Sprinkler piping installation will follow soon after.

The electrical contractor is running conduit throughout for power, lighting and AV systems. The electrical service is also being run to the mechanical room.

The masonry contractor is constructing more block walls on the acoustic shelf. They have poured about a quarter of the concrete floors.


Thursday, June 29, 2017

Structural Steel Completed

The structural steel for the first phase is complete. We will be pouring concrete on the roof deck and floor slabs in the next couple of weeks.



FOR MORE: See the live construction camera and more details about the project.

Thursday, June 15, 2017

The Frame Continues Taking Shape

Structural steel installation will continue for the next several weeks as more materials arrive. Columns, trusses and catwalks are being erected. Also, new HVAC equipment is being installed in the existing Wilmot mechanical room and should be completed in late July.
The steel trusses weigh 8,000 pounds each.


FOR MORE: See the live construction camera and more details about the project.