Thursday, June 29, 2017

Structural Steel Completed

The structural steel for the first phase is complete. We will be pouring concrete on the roof deck and floor slabs in the next couple of weeks.



FOR MORE: See the live construction camera and more details about the project.

Thursday, June 15, 2017

The Frame Continues Taking Shape

Structural steel installation will continue for the next several weeks as more materials arrive. Columns, trusses and catwalks are being erected. Also, new HVAC equipment is being installed in the existing Wilmot mechanical room and should be completed in late July.
The steel trusses weigh 8,000 pounds each.


FOR MORE: See the live construction camera and more details about the project.