Monday, February 19, 2018

Doors, Paint, and Equipment Going In

The latest:
  • The millwork contractors are installing the wood finishes to the building.
  • Doors are being installed.
  • Final painting is underway.
  • The theatrical equipment, lighting and AV is in progress.
  • Mechanical and electrical systems are nearing completion.
  • Wood flooring starts the week of Feb. 19.