The mechanical contractors are installing duct work in the Performance Hall. Sprinkler piping installation will follow soon after.
The electrical contractor is running conduit throughout for power, lighting and AV systems. The electrical service is also being run to the mechanical room.
The masonry contractor is constructing more block walls on the acoustic shelf. They have poured about a quarter of the concrete floors.