The mass excavation for the music performance hall is complete.
That means that truck traffic to the north side of campus will be greatly reduced — and the driveway to enter Parking Lot Q directly from East Avenue (the northernmost entrance) has re-opened to incoming traffic.
Photo: Workers are excavating and forming the footings for the foundation walls. |
Last week, construction of the building foundations began and is expected to take several more weeks.
Next: Masonry partitions construction will begin the week of April 3.
Next: Masonry partitions construction will begin the week of April 3.
Photo: Workers install reinforcing bars in a retaining wall that will be poured next week. That's Smyth Hall in the distant background. |
Continue to be careful when driving and walking through Parking Lot A, where a steady flow of deliveries and concrete trucks continues.