Monday, February 19, 2018

Doors, Paint, and Equipment Going In

The latest:
  • The millwork contractors are installing the wood finishes to the building.
  • Doors are being installed.
  • Final painting is underway.
  • The theatrical equipment, lighting and AV is in progress.
  • Mechanical and electrical systems are nearing completion.
  • Wood flooring starts the week of Feb. 19.





Friday, January 26, 2018

It's Starting to Come Together

The center is beginning to look less like a construction zone and more like a usable space. We're beginning to paint and have been installing ceilings, lighting, and plumbing fixtures. Installation of the flooring will begin in the next two weeks.


FOR MORE: See the live construction camera, a rendering of the building's exterior when finished, and more details about the project.

Wednesday, October 25, 2017

Those Blue Stripes are Temporary

In progress on the music performance center's exterior walls: the metal studs and the masonry. When finished, the building won't be gray with blue stripes!


Interior work: Installation of the sprinkler system, duct work, and mechanical piping.


Electrical pathways are mostly in place. Drywall partitions have begun. Roofing will continue next week and the last of the concrete floors will be poured as well.

FOR MORE: See the live construction camera, a rendering of the building's exterior when finished, and more details about the project.