Tuesday, May 30, 2017

Structural Steel Deliveries Begin

Over the next several weeks, multiple deliveries of steel are arriving. At times, this work may disrupt use of Lot A for parking. Look for more details about parking in future updates.




Saturday, May 13, 2017

Load-bearing Walls Completed

Photos this week show the structural masonry load-bearing walls being completed.


Everything is on schedule to start the structural steel around June 1.


We will soon be constructing the pathways to bring power and fiber to the building.  The area in the lawn north of the art studios will see increased construction activity as we tie into the existing utilities near Smyth. 


FOR MORE: See the live construction camera and more details about the project.